Question:
Your project is in the Activity Duration Estimating process. You ask your expert team members to come up with a worst-case scenario, a best-case scenario, and a most likely scenario for the duration of a specific phase of the project. When the team returns the duration estimates, you average the three to form a new duration estimate. What type of estimating technique are you using?
Answer:
should-cost;
analogous;
three-point;
parametric.